Kane Manufacturing has a division that produces two models of
hibachis, model A and model B. To produce each model A hibachi
requires 6 lb of cast iron and 12 min of labor. To produce each
model B hibachi requires 7 lb of cast iron and 6 min of labor. The
profit for each model A hibachi is $8, and the profit for each
model B hibachi is $7.50. If 2200 lb of cast iron and 40
labor-hours are available for the production of hibachis each week,
how many hibachis of each model should the division produce each
week to maximize Kane’s profit?
Please show work.

Show transcribed image text Kane Manufacturing has a division that produces two models of hibachis, model A and model B. To produce each model A hibachi requires 6 lb of cast iron and 12 min of labor. To produce each model B hibachi requires 7 lb of cast iron and 6 min of labor. The profit for each model A hibachi is $8, and the profit for each model B hibachi is $7.50. If 2200 lb of cast iron and 40 labor-hours are available for the production of hibachis each week, how many hibachis of each model should the division produce each week to maximize Kane's profit? model A model B hibachis hibachis What is the largest profit the company can realize? Is there any raw material left over? (If so, give the amount remaining. If not, enter 0.) cast iron labor lb labor-hr
Kane Manufacturing has a division that produces two models of hibachis, model A and model B. To produce each model A hibachi requires 6 lb of cast iron and 12 min of labor. To produce each model B hibachi requires 7 lb of cast iron and 6 min of labor. The profit for each model A hibachi is $8, and the profit for each model B hibachi is $7.50. If 2200 lb of cast iron and 40 labor-hours are available for the production of hibachis each week, how many hibachis of each model should the division produce each week to maximize Kane's profit? model A model B hibachis hibachis What is the largest profit the company can realize? Is there any raw material left over? (If so, give the amount remaining. If not, enter 0.) cast iron labor lb labor-hr